North Arlington Transportation Update
Utility work at roundabout project; Stormwater work at Langston Blvd. & N. Sycamore St.

Having trouble viewing this email? View it as a Web page.

Transportation Header

North Arlington Transportation Update

January 16, 2026


Visit the My Arlington map to learn about other projects in your area


Underground Utility Work Next Weekend

On January 22-24, crews will work on a conduit below Military Road on the north leg of the intersection with Nelly Custis Road. This work will take place between 8:00 AM and 5:00 PM.

  • The north northbound lane will close; all traffic will shift to the southbound lane in a flagging formation
  • Flaggers will guide vehicle traffic through the intersection
  • Sidewalks and crosswalks will remain open

 

Outside of work hours, the intersection will resume its all-way stop configuration through the end of Phase 3. Learn more on the project page.

DC17 - Miltary Road Roundabout Weekend Conduit Work

Stormwater Improvements Project on Langston Blvd.

Stormwater Langston and Sycamore - Jan-Feb 2026

The Arlington County Office of Sustainability and Environmental Management will be performing stormwater utility upgrades at the intersection of Langston Boulevard and North Sycamore Street.

 

Construction is expected to begin around January and February, 2026 and will last about 4-6 months.  The construction will require one lane closure on Sycamore St. and one on Langston Boulevard. The sidewalk will remain open during construction.

This project will increase stormwater system capacity by installing an additional 76”x48” stormwater pipe and two new stormwater structures at the intersection of Langston Boulevard and North Sycamore Street.

 

(This work is not related to the bus bay expansion project at East Falls Church Metro a few blocks south.)

 